On October 21, the Harvie Heights community hall was full. Residents came to question AltaLink about the 54L transmission line, and the Rocky Mountain Outlook reported that the meeting ended with several routes still in play and no answer on where the line will go. The line was built in 1941. It runs about 24 kilometres between Canmore and Banff, and AltaLink says the 138-kV line has reached the end of its service life.
Each route option near the hamlet puts its cost on something different. One affects the tree screen behind Bow River Drive. Another runs near the recharge area of the aquifer that supplies the hamlet's wells. A third crosses the habitat patch around the community, and the fourth follows the highway. As of the Outlook's November 2 report, the Harvie Heights Community Association was surveying residents to find out where the community stands among those options.
Four lines on the map
AltaLink's June 2026 project update lists the Harvie Heights options. Two follow the existing alignment, one rebuilt overhead and one buried. The other two came out of stakeholder feedback. The first runs along Highway 1, on an alignment that was originally studied for a temporary bypass and is now being considered as permanent. The second is a firebreak route on the east and north sides of the hamlet, inside Bow Valley Wildland Provincial Park.
The September update moved both of the new options. Parts of the Highway 1 route shifted about seven to 10 metres. Parts of the firebreak route shifted about 20 to 100 metres, and AltaLink determined that the firebreak route would need a right-of-way 20 metres wide. The current alignments are drawn on AltaLink's September 17 strip map, which is worth having open while reading the rest of this.
Why the poles may roughly double in height
The decision got harder in September. The Alberta Electric System Operator determined that the Banff area needs an additional circuit for reliability. AltaLink now proposes rebuilding about 15 kilometres of the 54L as a double circuit, from the 85L connection to the West Cascade substation, and it says a single-circuit option is no longer being considered for that stretch. AESO's project is called Transmission Enhancements in the Banff Area (3147). It started with a FortisAlberta request to improve service reliability in the Banff area.
An AESO spokesperson explained the reason in an email to the Rocky Mountain Outlook. Customers in the Banff, Lake Louise and Sunshine areas can lose power whenever the line is out of service, and "rebuilding the existing line alone will not address the reliability issues in the area."
For Harvie Heights, the result is taller structures. AltaLink describes the current 54L structures as about 15 to 20 metres tall. The double-circuit structures would be mostly self-weathering steel monopoles, with two-pole structures in some places, at roughly 16 to 35 metres. If any section goes underground, riser structures about 22 to 32 metres tall would stand at each end of it. In the possible Harvie Heights underground segment, concrete vaults about six metres long would sit within the existing right-of-way and stand up to one metre above ground.
The existing alignment, overhead: the trees on Bow River Drive
Some homes on Bow River Drive back onto the current line. Mike Bentley, vice-president of the community association, told the Outlook that taller structures would have a much greater visual impact, one "not going to affect just us that are along the power line, but... a lot of other people that are in the community as well."
The poles are only part of it. An overhead rebuild would also mean clearing more trees along the right-of-way. AltaLink is proposing vegetation control easements reaching up to 15 metres past each side of the existing right-of-way onto private property, down from the 25 metres it first gave residents. It says it needs to remove "danger trees" that could fall onto the line. Association president Howard Hepburn pointed out that those trees give shade, privacy and protection from wind and highway noise. "We'll be able to hear the highway twice as well from here," he told the Outlook. AltaLink said it would work with affected landowners to identify which trees need to come down and would negotiate compensation.
The existing alignment, underground: the cost question
Burying the line through the hamlet would mostly avoid clearing outside the existing right-of-way. In its June update, AltaLink wrote that underground lines can cost substantially more than overhead and disturb more ground.
The Outlook reported that underground lines can cost up to 10 times as much as overhead. At the October meeting, AltaLink representatives acknowledged that in Harvie Heights the cost of vegetation management and easements could be higher than the cost of going underground. AltaLink has not released route-by-route cost comparisons and says they will be in its application to the AUC. Buried cable has its own issue here, too. The same report noted that digging toward the aquifer is a concern along the existing alignment as well.
The firebreak: the aquifer and the slopes behind the hamlet
Moving the line away from the homes sounds like the obvious fix. The firebreak route is where the objections are most specific. Brendon Jones, AltaLink's manager of environment, said the firebreak has already been cleared for wildfire protection, so poles would add little to the habitat fragmentation that is already there. Tony Clevenger is a wildlife scientist who lives in the hamlet. He argued that the Harvie Heights habitat patch still matters to animals moving through the Bow Valley, and that the cleared firebreak grows back with berry shrubs bears feed on. Clevenger and wildlife expert Bill Hunt also pointed to the south-facing slopes behind Harvie Heights as winter habitat. Hunt noted that the Canmore Nordic Centre and the Rundle forebay and canal already restrict movement on the other side of the valley.
The hamlet's water is the second issue. Harvie Heights residents draw well water from an underground aquifer. Local geologist Louis Kamenka said the firebreak is near the aquifer's recharge area, and that deep holes for tall poles there have "a greater chance of them actually intersecting the aquifer." AltaLink said groundwater impacts are being assessed in the environmental evaluation it will submit to the AUC. It also said it would not build a permanent access road along the firebreak, and that crews would use existing trails and restore disturbed areas afterward.
The firebreak also has a fire-suppression problem. In a November 14 letter to the Outlook, Canmore resident Gary Dudinsky wrote from his wildfire suppression background. He argued that energized lines in the firebreak would limit both air tanker drops and ground crews' sprinklers and hoses, and he urged AltaLink to drop the alignment.
Highway 1: the edge the hamlet already has
That leaves the route along the Trans-Canada. Hepburn told the Outlook it looks promising, with "a lot less interference with the community and wildlife considerations and aquifer considerations." AltaLink is discussing the Highway 1 option with Alberta Transportation and Economic Corridors, and the firebreak option with Alberta Forestry and Parks. At the time of that November 2 report, the association had not endorsed a route, and its resident survey was how it planned to settle on one.
The same project in Canmore and the park
Harvie Heights is the middle of a longer line. AltaLink's June update puts about 8 kilometres of the rebuild in and around Canmore, where it proposes shifting the Palliser Trail segment about 16 metres east and is assessing an option behind the Canyon West Condominium near Elk Run Boulevard. Inside Banff National Park, Parks Canada conceptually supports a double circuit as long as visual impacts are addressed in high-value areas. That includes studying an underground option near Johnson Lake.
The next five weeks
AltaLink plans to file its facilities application with the AUC by the end of 2026. AESO is expected to file its application for the additional circuit, and the commission will consider the two together. Before filing, AltaLink is weighing environmental assessments, engineering, construction, cost and stakeholder feedback to pick a preferred route and an alternate. Residents can still take part in the commission's review once the applications are filed.
The 54L project page shows construction starting in late 2028 and finishing in 2031. Feedback goes to AltaLink's stakeholder relations team at [email protected] or 1-877-267-1453.
If you own in Harvie Heights and would like to look at the 54L strip map alongside your own property, Vincent & Wright Group is glad to sit down with you. Connect with a Canmore & Banff property specialist.